First, we still haven't heard from BGE about when they are going to run power. They did let Victor know that they inspected the pre-work they required of Bob Ward and that we are good to go. But they haven't returned calls from Victor, me, or Steve regarding when power will run to the house.
The cabinets in the kitchen that were incorrect have been ordered and will be delivered next Wednesday and installed that Friday. The subway tile back splash in the kitchen will be scheduled for probably Monday the following week. We're still waiting on a few random things inside the house to get done, but the only "big" thing that remains is flooring.
The most exciting update to share is that we finally have a stone-front house!!! Carlos (the stone guy) still has a few finishing touches to add tomorrow, but it is pretty much done. I'll take another picture tomorrow when his truck and scaffolding aren't in the way. All that's left for the exterior are shudders, painting the columns and door, and gutters.
![]() |
| Garage doors |
![]() |
| Start of stone! |
![]() |
| Stone almost done! |



No comments:
Post a Comment